Work resumes on Lilian Ngoyi Street as JRA targets October completion |
The reopened blast section is already carrying traffic, while work continues on the wider CBD street upgrade. |

Full-scale construction has resumed on Lilian Ngoyi Street after cash-flow problems interrupted the project, according to the Johannesburg Roads Agency.
In its 28 August 2026 update, the JRA said payments had been finalised and progress had reached 72%. The remaining work includes improvements to the road, pavements, stormwater infrastructure and lighting.
The agency now targets 31 October 2026, following the missed end-August deadline. It describes October as the earliest anticipated completion date, dependent on service providers being paid on time.
Part of the street is already back in use
The 450-metre section between Harrison and Wanderers streets, reconstructed after the July 2023 explosion, reopened in September 2025.
The wider project covers 1.8km between Ntemi Piliso and End streets. Alongside road and underground infrastructure work, plans include bus stops, street furniture and landscaping.
The completed section represents progress, although more than three years after the explosion, businesses and road users are still waiting for the broader upgrade to be finished.
Sections will reopen as work progresses
The JRA says closures between Wanderers and End streets will happen progressively, with completed sections reopened to traffic.
Intersections are expected to remain operational during these sectional closures. Localised restrictions on Lilian Ngoyi Street and partial closures on adjacent roads are planned through October.
If you are visiting a business or arranging a delivery, check access with your destination before setting off and allow extra travel time.
Spending and delivery remain under scrutiny
Daily Maverick reported on 6 September that R185 million had been paid to two contractors, citing figures supplied by the JRA.
This comprised R19 million paid to Step Up Engineering before its contract was terminated over performance concerns, and R166 million to replacement contractor Korone Engineering. The reported total project allocation is R230 million, with professional services covered by a separate contract.
For traders, completing the work is about restoring customer access too. Pie-shop operator Mohamed Yaseen told the publication that excavations, damaged pavements and parking difficulties were making it harder for people to reach his business.
The Bottom Line
The next useful signs of progress will be completed sections reopening and access improving along the street. Construction has resumed, but the October target still depends on timely payments and the remaining work being delivered. |
More from Joburg Insider

Sep 22, 2026
Privacy and access meet in the matric-results appeal
The Supreme Court of Appeal will hear a challenge over publishing results by examination number, with learners’ privacy and public access at the centre of the dispute.

Sep 22, 2026
More ways to get grant help
Online applications, WhatsApp support and free office Wi-Fi offer more ways to access grant services, while personal assistance remains available.

Sep 21, 2026
A chance paddle became a bigger ambition
The Gauteng kayaker has represented South Africa overseas and is developing her coaching skills alongside her own sporting ambitions.

Sep 21, 2026
Homemade carts take over Sandton Drive
The wild unpowered go kart race returns to Sandton Drive on 20 September 2026. Teams can still apply to compete.

0 Comments
Join the conversation
Be the first to comment
Share your thoughts above.