Work resumes on Lilian Ngoyi Street as JRA targets October completion

The reopened blast section is already carrying traffic, while work continues on the wider CBD street upgrade.

đź“…

đź“…

Sep 9, 2026

0 Comments
AI-generated image for illustrative purposes

Full-scale construction has resumed on Lilian Ngoyi Street after cash-flow problems interrupted the project, according to the Johannesburg Roads Agency.

 

In its 28 August 2026 update, the JRA said payments had been finalised and progress had reached 72%. The remaining work includes improvements to the road, pavements, stormwater infrastructure and lighting. 

 

The agency now targets 31 October 2026, following the missed end-August deadline. It describes October as the earliest anticipated completion date, dependent on service providers being paid on time.

 

Part of the street is already back in use

 

The 450-metre section between Harrison and Wanderers streets, reconstructed after the July 2023 explosion, reopened in September 2025.

 

The wider project covers 1.8km between Ntemi Piliso and End streets. Alongside road and underground infrastructure work, plans include bus stops, street furniture and landscaping. 

 

The completed section represents progress, although more than three years after the explosion, businesses and road users are still waiting for the broader upgrade to be finished.

 

Sections will reopen as work progresses

 

The JRA says closures between Wanderers and End streets will happen progressively, with completed sections reopened to traffic.

 

Intersections are expected to remain operational during these sectional closures. Localised restrictions on Lilian Ngoyi Street and partial closures on adjacent roads are planned through October. 

 

If you are visiting a business or arranging a delivery, check access with your destination before setting off and allow extra travel time.

 

Spending and delivery remain under scrutiny

 

Daily Maverick reported on 6 September that R185 million had been paid to two contractors, citing figures supplied by the JRA.

 

This comprised R19 million paid to Step Up Engineering before its contract was terminated over performance concerns, and R166 million to replacement contractor Korone Engineering. The reported total project allocation is R230 million, with professional services covered by a separate contract.

 

For traders, completing the work is about restoring customer access too. Pie-shop operator Mohamed Yaseen told the publication that excavations, damaged pavements and parking difficulties were making it harder for people to reach his business. 

 

The Bottom Line

 

The next useful signs of progress will be completed sections reopening and access improving along the street. Construction has resumed, but the October target still depends on timely payments and the remaining work being delivered.

0 Comments

Join the conversation

Be the first to comment

Share your thoughts above.

More from Joburg Insider

Joburg Insider

© 2026 Joburg Insider.

Your local guide that’s built just for you and your neighbourhood. Every edition brings you real local life: new restaurant openings, great places to eat, family‑friendly events, markets, gigs and things to do nearby. You’ll also get short, useful stories about local people, small businesses and community initiatives that make your area feel like home. We cut out generic, click‑baity content and outdated events, and focus on practical, trustworthy updates that help you decide where to go, what to try and how to stay connected in your community.